Uddevalla–Strömstad, replacement of overhead contact line system, including Uddevalla railway yard, and elevation of platform 2a3a at Uddevalla railway station

About the project

The project will include four measures:

  • Upgrading overhead contact line on the stretch Uddevalla–Strömstad
  • Upgrading overhead contact line upgrade at Uddevalla station
  • Elevating platform 2a3a at Uddevalla station
  • Multiduct operation facilities Rabbalshede–Strömstad.

Design consultant Systra Sverige AB is working on producing tender documents and construction documents.

Field work including environmental and geotechnical sampling has been carried out over the winter and spring. The sampling will provide the basis for continued planning in 2023.

Estimated production is planned for 2025–2026, where the work will take place in stages during total shutdown.

  • Uddevalla Bangård
  • Uddevalla–Rabbalshede
  • Rabbalshede–Strömstad

The work is expected to result in a more reliable facility, increased traffic safety for travellers and an accessible station environment.

Overhead contact line upgrade on the stretch Uddevalla–Strömstad and Uddevalla station

The overhead contact line system between Uddevalla and Strömstad dates from 1950, and the posts and piers that have stood since then are in need of replacement. The overhead contact line system at Uddevalla railway station is just as old, and the rusted bridges also need to be replaced.

Elevating platform 2a3a in Uddevalla station

The platform for track 2a3a in Uddevalla is low and uneven. This means that the distance from platform to train is too large, making the platform inaccessible to the disabled and a safety risk for all passengers boarding and disembarking the trains. The project will therefore include raising and equipping the platform, and providing it with a roof, in order to meet current requirements as well as future regulations. These measures will also lead to better lighting, accessibility and clear signs with traffic information.

 

Timeline

  1. Producing tender and construction documents – 2023
  2. Construction tender documents will be published in winter 2024
  3. Start of construction – 2025
  4. Finished – 2026

 

Foundation laying with drill train on one of Trafikverket’s projects in 2021.Foto: Daniel Svensson
Work with contact over line installation using rail backhoe loaders with baskets on one of Trafikverket’s projects in 2021.Foto: Daniel Svensson