Procurement regarding E6.21 Lundbyleden, Streets at Backaplan, Bohusbanan and Brunnsbo station
Below you will find details regarding procurement of the project.
Time schedule for procurement
The first contract, E1, starts: Q4 2024.
The second contract, E2, starts: Q1 2025.
The fourth contract, E4, starts: Q1 2025.
The third contract, E3, starts: Q2 2026.
Procurement information
E1: Invitation to participate will be published in Q4 2023.
E2: Invitation to participate will be published in Q4 2023.
E4: Tender documents will be published in Q3 2024.
E3: Tender documents will be published in Q4 2024.
Tender documents will be published accordingly.
E1: Tenders in Q3 2024.
E2: Tenders in Q1 2025.
E4: Tenders in Q1 2025.
E3: Tenders in Q2 2026.
The contracts for the project will be procured in several detailed designed execution contracts and these are planned to be procured during 2023–2026.
For more information about the upcoming procurement, please take a look at Trafikverket’s procurement plan.