Procurement regarding E6.21 Lundbyleden, Streets at Backaplan, Bohusbanan and Brunnsbo station

Below you will find details regarding procurement of the project.

Time schedule for procurement

  • Tender documents for the Design & Build contract are planned to be published in May 2021
  • Project reviews are planned to be held on the 7th–1th of  June 2021
  • Planned tender period for Design and Build contract is May 2021–November 2021
  • Planned start of contract is in February 2022
  • Planned completion in 2027.

For more information about the upcoming procurement, please take a look at Trafikverket’s procurement plan.

Planned procurements

Documents from the information meeting for Swedish suppliers

The information meeting was held via Skype on the 9th of February 2021.

Questions and answers during the information meeting can be found in the presentation.

Presentation from information meeting in Swedish (pdf, 783 kB)

Documents from information meetings with international suppliers

The information meetings were held via Skype at two occasions, the 11th and the 12th of  February 2021.

Questions and answers during the information meeting can be found in the presentation.

Presentation from both information meetings in English (pdf, 825 kB)